Project Location Date
12 GeV CEBAF Upgrade TJNAF 4/8-10/14
National Synchrotron Light Source (NSLS-II) Mini-Review GTN 4/18/14
Renovate Science Laboratories (RSL-II) BNL 4/24/14
U.S. Contributions to ITER Project Mini-Review GTN 4/29/14
Utilities Infrastructure Modernization (UIM) TJNAF 5/6/14
Large Synoptic Survey Telescope (LSST) SLAC 5/6-7/14
Research Support Bldg (RSB) Mini-Review SLAC 5/20/2014
Science and User Support Bldg (SUSB) Mini-Review SLAC 5/21/2014
Seismic Phase II Mini-Review LBNL 5/22/2014
Facility for Rare Isotope Beams (FRIB) MSU 6/24-26/14
ANL Leadership Computing Facility (ALCF-3) ANL 7/29-30/14
Muon g–2  FNAL 7/29-31/14
STAR Heavy Flavor Tracker (HFT) BNL 7/31/2014
LHC CMS Detector Upgrade FNAL 8/5-7/14
SNS Instruments Next Generation II (SING II) ORNL 8/5-6/14
ORNL Leadership Computing Facility (OLCF-4) ORNL 8/19-20/14
LHC ATLAS Detector Upgrade BNL 9/16-18/14
Large Synoptic Survey Telescope (LSST) SLAC 11/4-6/14