NSLS-II Experimental Tools (NEXT) BNL 5/31-6/1/ 2017
Gamma Ray Energy Tracking Array (GRETA) LBNL 4/25-27/2017
12 GeV CEBAF Upgrade TJNAF 5/10-11/2017
U.S. Contributions to ITER Project ORNL 5/16-18/2017
Proton Power Upgrade (PPU) ORNL 5/23-25/2017
Linac Coherent Light Source II (LCLS-II) SLAC 6/13-15/2017
Facility for Rare Isotope Beams (FRIB) MSU 6/27-29/2017
National Energy Research Scientific Computing Center (NERSC) LBNL 6/27-28/2017
Photon Science Laboratory Building (PSLB) SLAC 6/27-28/2017
Exascale Computing Project (ECP) ORNL 7/11-13/2017
SuperCDMS/SNOLAB SLAC 7/18-20/2017
Argonne Leadership Computing Facility (ALCF) GTN 7/25-26/2017
Muon to Electron Conversion Experiment (Mu2e) FNAL 7/25-27/2017
HL-LHC Accelerator Upgrade (HL-LHC AUP) FNAL 8/8-10/2017
Oak Ridge Leadership Computing Facility (OLCF) ORNL 8/15-16/2017
Mid-Scale Dark Energy Spectroscopic Instrument (DESI) LBNL 9/12-14/2017
Super Pioneering High Energy Nuclear Interaction eXperiment (sPHENIX) BNL 11/2017 TBD
Facility for Rare Isotope Beams (FRIB) MSU 12/5-7/2017